Warning: "continue" targeting switch is equivalent to "break". Did you mean to use "continue 2"? in /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/revslider/includes/operations.class.php on line 2858 Warning: "continue" targeting switch is equivalent to "break". Did you mean to use "continue 2"? in /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/revslider/includes/operations.class.php on line 2862 Warning: "continue" targeting switch is equivalent to "break". Did you mean to use "continue 2"? in /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/revslider/includes/output.class.php on line 3708 Warning: Cannot modify header information - headers already sent by (output started at /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/revslider/includes/operations.class.php:2858) in /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/onecom-vcache/vcaching.php on line 522 Warning: Cannot modify header information - headers already sent by (output started at /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/revslider/includes/operations.class.php:2858) in /customers/e/4/4/buildersqatar.com/httpd.www/wp-content/plugins/onecom-vcache/vcaching.php on line 529 EPIC for Mesaieed (Mic) Hazardous Waste Treatment Center (HWTC) Compliance

EPIC for Mesaieed (Mic) Hazardous Waste Treatment Center (HWTC) Compliance

Client:
Qatar Petroleum
Consultant:
Qatar Petroleum
Location:
Mesaieed, Qatar
Status:
Completed
Period:
from 08.2017 to 03.2019
Project Detail

The Scope of Works Consists of:

  • Design & construction of chemical storage building (including civil, architectural, MEP works).
  • Design & construction of concrete foundation (70×75) for chemical waste storage including collection pit, holding tank.
  • Design, installation of new underground fire water line to connect to existing fire water line including GRE Pipes, valves, hydrant, thrust blocks & chamber.
  • Design & construction of access road for the chemical waste storage.
  • Installation of thrust block to the existing fire line.
  • Replacement of valves for the existing fire water.